On an airport expansion we worked on, running a Constructability Review during accelerated design stages uncovered conflicts in steel sequencing and service routing. Despite the compressed timeline, those adjustments prevented major clashes onsite that would have been far more costly. Even under schedule pressure, pausing briefly for review avoided cascading delays. It reinforced the principle that buildability analysis pays off even when time is tight.